Oregon Lien Calculator: How Many Days Do You Have Left to File?

This free Oregon lien calculator is set to Oregon. Enter your first and last days on the job to see how many days you have left to file a mechanics lien in Oregon, and every notice and bond-claim date before it, counted to the calendar day.

  1. Choose the state where the property is.
  2. Enter your first and last day of work or materials on the job.
  3. Add the lien recording date or the owner’s notice of completion if you have them.
  4. Read your deadlines, soonest first.
Choose a state and enter a date to see your deadlines.

Subcontractor, supplier, public or federal job? See your deadlines by role and project type →

This is an estimate, not legal advice. Day-counts are the general rule LienWarden tracks for each state; your role, the property type and the notice method can change them.

Save this project in LienWarden. LienWarden keeps every one of these dates for the project in one list and drafts the notice or demand letter when one comes due. Your first project is free and you can start without an account.

Oregon lien deadlines LienWarden tracks

DeadlineDaysCounted from
Preliminary notice8 daysyour first day of labor or materials
Notice of intent to lien10 dayscompletion or your last day of furnishing
Record the mechanics lien75 dayscompletion or your last day of furnishing
File the enforcement suit120 daysthe day the lien was recorded
Payment-bond claim (bonded and public jobs)180 dayscompletion or your last day of furnishing
Act after the owner's notice of completion30 daysthe owner's recorded notice of completion

Governing statute: Or. Rev. Stat. § 87.001 et seq.. These are the general day-counts LienWarden tracks for Oregon. Your role, the property type and the delivery method can change them, so confirm with the statute or a construction attorney before you rely on a date. The full rule table, nearby states and a printable view are on the Oregon lien deadlines page.

Working in another state? Use the lien calculator for all 50 states.

Questions

How long do you have to file a mechanics lien in Oregon?

In the rules LienWarden tracks, Oregon gives 75 days from completion or your last day of furnishing to record the lien. Enter your dates above to see the exact calendar date and how many days are left.

When is the Oregon preliminary notice due?

LienWarden tracks 8 days from your first day of labor or materials for Oregon. Some claimants and project types have different notice duties, so check the statute for your role.

How long do I have to enforce a Oregon lien?

LienWarden tracks 120 days from the day the lien is recorded to file the enforcement suit in Oregon. If you miss it, the lien generally expires.

Is this calculator legal advice?

No. This is an estimate, not legal advice. It applies general day-counts and can’t account for every exception, so verify your deadline with the statute or a construction attorney before you rely on it.