Notice of Intent to Lien PDF: Which Deadline Applies to You?
Short answer: a notice of intent to lien is a written warning that you will record a mechanics lien if you are not paid by a stated date. You can download a free notice of intent to lien PDF template (free account), fill in the project, the amount and the deadline, and send it by a method you can prove. Which deadline applies depends on your state: in some states the notice is a legal step you must take before filing, and in the rest it is an optional demand letter that often gets the bill paid without a lien.
The fastest way to get your own date is the lien calculator. Pick the state, enter your last day on the job, and it shows the notice of intent date LienWarden tracks next to the lien recording deadline.
What a notice of intent to lien is
It is not the lien itself. It is the last letter before the lien. It tells the owner, and usually the general contractor, that you furnished labor or materials, how much is unpaid, and that you will record a lien against the property if the balance is not paid. Owners react to it because a recorded lien clouds their title and can hold up a sale or a construction loan draw.
Other names for the same document: notice of intent to file a lien, intent to lien letter, pre-lien notice, and notice of intention to file lien. A preliminary notice is a different document. It goes out at the start of the job to preserve your rights. The notice of intent goes out near the end, when payment is late.
Required or optional? 50-state notice of intent table
The table shows the notice of intent date LienWarden tracks in each state (days after your last furnishing or completion) and the lien recording deadline from the same rules. Two states were checked against the statute text today and are marked as required. For the others, the statute that governs the notice is listed so you can confirm whether your state makes the notice mandatory and how many days it must come before the lien. Treat the tracked date as the latest safe day to send it, not a target.
| State | Notice of intent date we track | Lien recording deadline | Mandatory status |
|---|---|---|---|
| Alabama | 10 days | 180 days | Confirm in Ala. Code § 35-11-210 et seq. |
| Alaska | 15 days | 90 days | Confirm in Alaska Stat. § 34.35.050 et seq. |
| Arizona | 20 days | 120 days | Confirm in Ariz. Rev. Stat. § 33-981 et seq. |
| Arkansas | 10 days | 120 days | Confirm in Ark. Code Ann. § 18-44-101 et seq. |
| California | 10 days | 90 days | Confirm in Cal. Civ. Code § 8000 et seq. |
| Colorado | 10 days | 120 days | Confirm in Colo. Rev. Stat. § 38-22-101 et seq. |
| Connecticut | 15 days | 90 days | Confirm in Conn. Gen. Stat. § 49-33 et seq. |
| Delaware | 10 days | 180 days | Confirm in 25 Del. Code § 2701 et seq. |
| Florida | 45 days | 90 days | Confirm in Fla. Stat. ch. 713, pt. I (Construction Lien Law) |
| Georgia | 30 days | 90 days | Confirm in O.C.G.A. § 44-14-360 et seq. |
| Hawaii | 10 days | 45 days | Confirm in Haw. Rev. Stat. § 507-41 et seq. |
| Idaho | 10 days | 90 days | Confirm in Idaho Code § 45-501 et seq. |
| Illinois | 90 days | 120 days | Confirm in 770 ILCS 60 (Mechanics Lien Act) |
| Indiana | 10 days | 90 days | Confirm in Ind. Code § 32-28-3 |
| Iowa | 30 days | 90 days | Confirm in Iowa Code ch. 572 |
| Kansas | 10 days | 120 days | Confirm in Kan. Stat. Ann. § 60-1101 et seq. |
| Kentucky | 10 days | 180 days | Confirm in Ky. Rev. Stat. § 376.010 et seq. |
| Louisiana | 10 days | 60 days | Confirm in La. Rev. Stat. § 9:4801 et seq. (Private Works Act) |
| Maine | 10 days | 90 days | Confirm in 10 M.R.S. § 3251 et seq. |
| Maryland | 10 days | 180 days | Confirm in Md. Code, Real Prop. § 9-101 et seq. |
| Massachusetts | 10 days | 90 days | Confirm in Mass. Gen. Laws ch. 254 |
| Michigan | 10 days | 90 days | Confirm in Mich. Comp. Laws § 570.1101 et seq. (Construction Lien Act) |
| Minnesota | 10 days | 120 days | Confirm in Minn. Stat. § 514.01 et seq. |
| Mississippi | 10 days | 90 days | Confirm in Miss. Code Ann. § 85-7-401 et seq. |
| Missouri | 10 days | 180 days | Confirm in Mo. Rev. Stat. § 429.010 et seq. |
| Montana | 10 days | 90 days | Confirm in Mont. Code Ann. § 71-3-521 et seq. |
| Nebraska | 10 days | 120 days | Confirm in Neb. Rev. Stat. § 52-125 et seq. (Construction Lien Act) |
| Nevada | 15 days | 90 days | Confirm in Nev. Rev. Stat. ch. 108 |
| New Hampshire | 10 days | 120 days | Confirm in N.H. Rev. Stat. § 447:2 et seq. |
| New Jersey | 10 days | 90 days | Confirm in N.J.S.A. § 2A:44A-1 et seq. (Construction Lien Law) |
| New Mexico | 10 days | 90 days | Confirm in N.M. Stat. § 48-2-1 et seq. |
| New York | 30 days | 240 days | Confirm in N.Y. Lien Law art. 2 |
| North Carolina | 10 days | 120 days | Confirm in N.C. Gen. Stat. ch. 44A, art. 2 |
| North Dakota | 10 days | 90 days | Confirm in N.D. Cent. Code ch. 35-27 |
| Ohio | 10 days | 75 days | Confirm in Ohio Rev. Code ch. 1311 |
| Oklahoma | 10 days | 120 days | Confirm in Okla. Stat. tit. 42, § 141 et seq. |
| Oregon | 10 days | 75 days | Confirm in Or. Rev. Stat. § 87.001 et seq. |
| Pennsylvania | 30 days | 180 days | Confirm in 49 P.S. § 1101 et seq. (Mechanics' Lien Law of 1963) |
| Rhode Island | 10 days | 200 days | Confirm in R.I. Gen. Laws § 34-28-1 et seq. |
| South Carolina | 10 days | 90 days | Confirm in S.C. Code § 29-5-10 et seq. |
| South Dakota | 10 days | 120 days | Confirm in S.D. Codified Laws ch. 44-9 |
| Tennessee | 10 days | 90 days | Confirm in Tenn. Code Ann. § 66-11-101 et seq. |
| Texas | 30 days | 105 days | Confirm in Tex. Prop. Code ch. 53 |
| Utah | 10 days | 90 days | Confirm in Utah Code § 38-1a-101 et seq. |
| Vermont | 10 days | 180 days | Confirm in 9 V.S.A. § 1921 et seq. |
| Virginia | 10 days | 90 days | Confirm in Va. Code § 43-1 et seq. |
| Washington | 30 days | 90 days | Confirm in Wash. Rev. Code ch. 60.04 |
| West Virginia | 10 days | 100 days | Confirm in W. Va. Code § 38-2-1 et seq. |
| Wisconsin | 30 days | 180 days | Required: at least 30 days before filing (Wis. Stat. 779.06(2), read 2026-11-01) |
| Wyoming | 20 days | 120 days | Required: at least 20 days before filing (Wyo. Stat. 29-2-107, read 2026-11-01) |
Day counts are the general rule for each state and are measured from completion or your last day of furnishing. Your role, the property type and the delivery method can change them. Each state name links to that state's full rule table.
How to fill out the PDF template
- Your business: legal name, address, and license number if your state requires one on lien documents.
- The property: street address, and the legal description or parcel number if you have it from the county records.
- The owner and the party who hired you: names and mailing addresses. Send a copy to the general contractor and the lender if you know them.
- What you furnished: a one-line description of the labor or materials and your first and last dates on the job.
- The amount: the unpaid balance, including retainage and approved change orders. Do not pad it. An inflated amount can void a lien in some states.
- The deadline: the date by which you must be paid before you record the lien. Make it earlier than your lien recording deadline, with enough room to prepare and record the lien if payment does not come.
- Signature and date.
How to send it so it counts
Delivery is where good notices fail. Use a method that produces proof of the date it was sent and received:
- Certified mail, return receipt requested is accepted in most states and is the safest default. Wyoming's statutory form, for example, is headed "certified mail, return receipt requested."
- Personal delivery works when you get a signed acknowledgment.
- Email is fast and is fine as a courtesy copy, but do not rely on it alone where the statute names a delivery method.
Keep a copy of the notice, the mailing receipt and the return card in the project file. If you end up recording the lien, you may need to prove the notice went out on time.
What happens after you send it
Most payers respond in one of three ways: they pay, they ask for a lien waiver in exchange for payment, or they dispute the amount. If they pay, trade a conditional waiver for the check and an unconditional one only after the money clears. If they do nothing, your lien recording deadline keeps running. The notice does not extend it. Record the lien before that date or the right is lost for that job.
Notice of intent vs other construction notices
| Document | When it goes out | What it does |
|---|---|---|
| Preliminary notice | Start of the job | Preserves lien rights in states that require it |
| Notice of intent to lien | After payment is late, before the lien | Final demand, and a legal precondition in some states |
| Mechanics lien | Before the recording deadline | Puts a claim on the property's title |
| Payment bond claim | Bonded and public jobs | Claims against the surety instead of the property |
Sending it with LienWarden
LienWarden computes the notice of intent and lien dates for each project from your dates, drafts the notice in your business name, and on paid plans emails it to the payer. USPS certified mail is a flat $19 a letter. Levelset charges $59 per recipient for its Send Notice service (levelset.com/pricing, checked 2026-10-25); see the Levelset alternative comparison. Your first project is free. Start free.
Questions people ask
Is a notice of intent to lien required?
In some states, yes. Wisconsin requires written notice at least 30 days before filing the lien claim (Wis. Stat. 779.06(2)), and Wyoming requires it at least 20 days before filing the lien statement (Wyo. Stat. 29-2-107). In many other states it is optional, but it still often gets the bill paid. Check the statute for your state in the table above.
How many days before filing a lien do you send a notice of intent?
It depends on the state. Where the notice is required, the statute sets a minimum number of days before you can record the lien. Use the lien calculator to see the notice and lien dates for your state, then send the notice early enough that the waiting period ends before your lien deadline.
Can I send a notice of intent to lien by email?
Email is a useful courtesy copy, but where a statute names a delivery method, such as certified mail, use that method and keep the receipt. Proof of delivery date is what makes the notice count.
Does a notice of intent extend my lien deadline?
No. The lien recording deadline keeps running after you send the notice. If you are not paid, record the lien before that deadline.
Where can I get a free notice of intent to lien PDF?
LienWarden has a free fillable notice of intent to lien template. Downloading it requires a free account.
Stop chasing invoices. Start collecting.
LienWarden computes every lien deadline in all 50 states from your project dates, then drafts and delivers the demand letters and notices — email included with paid plans, certified mail $19 flat. Your first active project is free.
Start free — no card requiredUse LienWarden free
Your first active project is free. LienWarden computes every notice and lien deadline in all 50 states from your project dates and drafts the documents.
Use LienWarden free →