Mechanics lien rights in Texas come from Tex. Prop. Code ch. 53, and they run on a clock: 45 days from first furnishing to serve the preliminary notice, 105 days from completion to record the lien itself, and 365 days from recording to file the enforcement suit. Miss any one of those windows and an otherwise-solid unpaid invoice usually drops to an unsecured debt. The calculator and table below turn those windows into the actual calendar dates for your project.
Texas license & bond renewal data is live in our free renewal lookup.
Enter the dates you have — we compute every TX deadline from the day-counts below. Dates stay in your browser.
Want these watched automatically — with the demand letter or notice drafted AND delivered for you (email included on paid plans, certified mail $19)? Start a free LienWarden trial →
| Deadline | Window | Counted from |
|---|---|---|
| Preliminary notice | 45 days | first furnishing of labor or materials |
| Notice of intent to lien | 30 days | project completion / last furnishing |
| Record the mechanics lien | 105 days | project completion |
| File the enforcement (foreclosure) suit | 365 days | recording the lien |
| Payment-bond claim (public/bonded jobs) | 90 days | project completion |
| Respond to a notice of completion | 30 days | the owner's notice of completion |
Day-counts are the general rule LienWarden tracks for Texas under Tex. Prop. Code ch. 53; statutes carry exceptions (residential vs commercial, owner-occupied, notice methods). Always verify against the current statute.
Other southwest states: Arizona · New Mexico · Oklahoma · all 50 states
Drop your email and we'll send you the TX cheat sheet now, plus 60/30/7-day alerts when you add your first project. No spam, unsubscribe anytime.
Add a project in 3 minutes. The agent computes these dates, drafts the payment demand letter or notice in your business name, and delivers it — email included on paid plans, USPS Certified Mail with tracking $19. from $12.99/mo — 50% off for 12 months with code FOUNDING50.
Start free trial →