Mechanic's Lien Deadlines by State: 26 States Give You 90 Days or Less
Across all 50 states the median window to record a mechanic's lien is 90 days after completion, and 26 states allow 90 days or less.
Key findings
- 26 of 50 states give a contractor or supplier 90 days or less after completion to record a lien; 40 states allow 120 days or less.
- Hawaii has the shortest recording window at 45 days, followed by Louisiana (60) and Ohio and Oregon (75 each).
- New York has the longest at 240 days, then Rhode Island (200).
- The median recording window is 90 days; 90 days is the most common rule (22 states).
- Recording is only half the clock: the median time to file a foreclosure suit after recording is 365 days, and Rhode Island allows only 40 days.
- Counting both clocks, a claimant in Hawaii has 135 days from completion to enforce; in North Dakota it is 1185 days.
Full data
Download the CSV (50 rows). Free to reuse with a link to this page (CC BY 4.0).
| State | State name | Days to record lien (from completion) | Days to enforce (from recording) | Total days | Statute |
|---|---|---|---|---|---|
| AK | Alaska | 90 | 180 | 270 | Alaska Stat. § 34.35.050 et seq. |
| AL | Alabama | 180 | 180 | 360 | Ala. Code § 35-11-210 et seq. |
| AR | Arkansas | 120 | 450 | 570 | Ark. Code Ann. § 18-44-101 et seq. |
| AZ | Arizona | 120 | 180 | 300 | Ariz. Rev. Stat. § 33-981 et seq. |
| CA | California | 90 | 90 | 180 | Cal. Civ. Code § 8000 et seq. |
| CO | Colorado | 120 | 180 | 300 | Colo. Rev. Stat. § 38-22-101 et seq. |
| CT | Connecticut | 90 | 365 | 455 | Conn. Gen. Stat. § 49-33 et seq. |
| DE | Delaware | 180 | 365 | 545 | 25 Del. Code § 2701 et seq. |
| FL | Florida | 90 | 365 | 455 | Fla. Stat. ch. 713, pt. I (Construction Lien Law) |
| GA | Georgia | 90 | 365 | 455 | O.C.G.A. § 44-14-360 et seq. |
| HI | Hawaii | 45 | 90 | 135 | Haw. Rev. Stat. § 507-41 et seq. |
| IA | Iowa | 90 | 730 | 820 | Iowa Code ch. 572 |
| ID | Idaho | 90 | 180 | 270 | Idaho Code § 45-501 et seq. |
| IL | Illinois | 120 | 730 | 850 | 770 ILCS 60 (Mechanics Lien Act) |
| IN | Indiana | 90 | 365 | 455 | Ind. Code § 32-28-3 |
| KS | Kansas | 120 | 365 | 485 | Kan. Stat. Ann. § 60-1101 et seq. |
| KY | Kentucky | 180 | 365 | 545 | Ky. Rev. Stat. § 376.010 et seq. |
| LA | Louisiana | 60 | 365 | 425 | La. Rev. Stat. § 9:4801 et seq. (Private Works Act) |
| MA | Massachusetts | 90 | 90 | 180 | Mass. Gen. Laws ch. 254 |
| MD | Maryland | 180 | 365 | 545 | Md. Code, Real Prop. § 9-101 et seq. |
| ME | Maine | 90 | 120 | 210 | 10 M.R.S. § 3251 et seq. |
| MI | Michigan | 90 | 365 | 455 | Mich. Comp. Laws § 570.1101 et seq. (Construction Lien Act) |
| MN | Minnesota | 120 | 365 | 485 | Minn. Stat. § 514.01 et seq. |
| MO | Missouri | 180 | 180 | 360 | Mo. Rev. Stat. § 429.010 et seq. |
| MS | Mississippi | 90 | 180 | 270 | Miss. Code Ann. § 85-7-401 et seq. |
| MT | Montana | 90 | 730 | 820 | Mont. Code Ann. § 71-3-521 et seq. |
| NC | North Carolina | 120 | 180 | 300 | N.C. Gen. Stat. ch. 44A, art. 2 |
| ND | North Dakota | 90 | 1,095 | 1,185 | N.D. Cent. Code ch. 35-27 |
| NE | Nebraska | 120 | 730 | 850 | Neb. Rev. Stat. § 52-125 et seq. (Construction Lien Act) |
| NH | New Hampshire | 120 | 365 | 485 | N.H. Rev. Stat. § 447:2 et seq. |
| NJ | New Jersey | 90 | 365 | 455 | N.J.S.A. § 2A:44A-1 et seq. (Construction Lien Law) |
| NM | New Mexico | 90 | 730 | 820 | N.M. Stat. § 48-2-1 et seq. |
| NV | Nevada | 90 | 180 | 270 | Nev. Rev. Stat. ch. 108 |
| NY | New York | 240 | 365 | 605 | N.Y. Lien Law art. 2 |
| OH | Ohio | 75 | 365 | 440 | Ohio Rev. Code ch. 1311 |
| OK | Oklahoma | 120 | 365 | 485 | Okla. Stat. tit. 42, § 141 et seq. |
| OR | Oregon | 75 | 120 | 195 | Or. Rev. Stat. § 87.001 et seq. |
| PA | Pennsylvania | 180 | 730 | 910 | 49 P.S. § 1101 et seq. (Mechanics' Lien Law of 1963) |
| RI | Rhode Island | 200 | 40 | 240 | R.I. Gen. Laws § 34-28-1 et seq. |
| SC | South Carolina | 90 | 180 | 270 | S.C. Code § 29-5-10 et seq. |
| SD | South Dakota | 120 | 730 | 850 | S.D. Codified Laws ch. 44-9 |
| TN | Tennessee | 90 | 365 | 455 | Tenn. Code Ann. § 66-11-101 et seq. |
| TX | Texas | 105 | 365 | 470 | Tex. Prop. Code ch. 53 |
| UT | Utah | 90 | 180 | 270 | Utah Code § 38-1a-101 et seq. |
| VA | Virginia | 90 | 180 | 270 | Va. Code § 43-1 et seq. |
| VT | Vermont | 180 | 180 | 360 | 9 V.S.A. § 1921 et seq. |
| WA | Washington | 90 | 240 | 330 | Wash. Rev. Code ch. 60.04 |
| WI | Wisconsin | 180 | 730 | 910 | Wis. Stat. § 779.01 et seq. |
| WV | West Virginia | 100 | 180 | 280 | W. Va. Code § 38-2-1 et seq. |
| WY | Wyoming | 120 | 180 | 300 | Wyo. Stat. § 29-2-101 et seq. |
Methodology
Deadlines come from LienWarden's 50-state rules table, compiled from each state's mechanic's lien statute (cited per state in the table) and last reviewed on 2026-10-23. Each figure is the general rule for a subcontractor or supplier on a private commercial project, counted in calendar days from completion or last furnishing as the statute defines it. Many states use different clocks for residential work, for direct contractors, or after a recorded notice of completion, and some (Texas, for example) count by months, so these figures are a comparison baseline, not legal advice. Check the statute or an attorney before relying on any single deadline.
Sources