Subcontractor Not Paid by GC: Know Your 90-Day Recovery Window
When a general contractor doesn't pay you, sitting still costs money. You have specific deadlines—typically 30 to 90 days depending on your state and project type—to file notices and liens that protect your right to recover. Miss those deadlines and you lose your easiest remedies. Here's the action sequence that keeps you in the game.
Your Recovery Timeline: 90 Days from Last Work
Your mechanics lien deadline starts when you last furnished labor or materials to the project. In most states, you have 90 days from that date to record a lien against the property. But before that final deadline, earlier dates determine whether you keep lien rights at all. These earlier deadlines vary by state and project type.
Step 1: Send Written Demand Now
Before filing anything formal, send a written demand to the GC stating the amount owed, invoice dates, and work performed. Use certified mail or email with read receipt. This creates a clear record. Many non-payments result from lost paperwork, not fraud. A demand often triggers payment within 10 days.
Step 2: Check Your Preliminary Notice Deadline
Many states require subcontractors to file a preliminary notice to the property owner, lender, and other parties within a window from their first work. This window varies—typically 10 to 30 days depending on the state. If you haven't filed it and that deadline hasn't passed, file immediately. Without preliminary notice in states that require it, your mechanics lien filing later becomes void, even if you file it within 90 days. The preliminary notice is not optional in those jurisdictions.
Federal projects follow different rules under the Miller Act and FAR. Written notice to the contractor is typically required within 90 days of your first delivery, but the format and recipients differ from state preliminary notices.
Step 3: Determine If a Payment Bond Exists
Ask the GC directly: Is there a payment bond on this project? Payment bonds are common on public projects, government work, schools, and many commercial builds. They are insurance agreements that obligate a third party (the surety/bond issuer) to pay subs and suppliers if the GC defaults. Bond claims have notice deadlines—typically 30 to 90 days—that run separately from your lien timeline. Missing a bond deadline doesn't affect your lien rights, but it eliminates that faster recovery path.
Step 4: File Your Mechanics Lien Before Day 90
If you reach 60 days unpaid, file your mechanics lien. Don't wait until day 85. Recording, notarization, and document preparation take time. The lien must be filed in the county recorder's office where the property sits. Once recorded, the property owner cannot refinance or sell without resolving it. This creates immediate pressure on the GC.
The lien itself is a formal document with strict formatting requirements that vary by state. It typically includes property description, amounts claimed, your contact information, dates of work, and the GC's information.
Worked Example: 90-Day Sequence in Action
You're a masonry sub. You finish work June 15, invoice June 20. No payment arrives. Here's what happens:
- July 10 (20 days unpaid): Send written demand by certified mail.
- July 15: Check preliminary notice deadline. If your state requires filing within 10 days of June 15, that deadline passed. If it allows 15 or 30 days, file the notice immediately if not already done.
- July 18: Ask the GC: "Is there a payment bond?" If yes, note the bond notice deadline and issuer information.
- August 5 (51 days unpaid): File mechanics lien. It's recorded August 6.
- August 10: The property owner's lender calls the GC. No refinance closes while a lien exists. GC feels pressure.
- August 28: GC resolves the dispute. Payment received September 2.
If you waited until September 10 to file, you'd miss the 90-day window (September 14) and lose lien rights entirely. Recovery would then require court action—slower and more expensive.
Variations That Change Your Deadlines
Project type and location affect which tools you can use and when deadlines expire.
- Retainage situations: If the contract holds back a percentage until project completion, your 90-day clock still runs from your last work date, not from retainage release. Don't assume retainage timing extends your lien window.
- Payment bonds on the same project: If both a mechanics lien and payment bond exist, they have separate deadlines and targets. File the bond notice first if its deadline is sooner (often 30 days), then file the lien (up to 90 days).
- Multi-state projects: Large projects spanning multiple states use the rules of each state's property location, not where the GC is based. File separately in each state where the property sits.
- Conditional waivers: Some GCs use joint checks or conditional waivers that tie your lien rights to future payment. Don't sign unconditional waivers until paid in full.
Mistakes That Eliminate Recovery
- Skipping preliminary notice when required: Your state may mandate it. Skip it, file a perfect lien, and discover later that the lien is void.
- Filing too close to the 90-day deadline: File by day 60. Recording delays, notarization errors, and address corrections can push you past deadline.
- Recording in the wrong county: The property location determines the correct recorder's office, not your business location.
- Signing an unconditional waiver early: Some GCs request waivers before final payment. Never waive lien rights until payment clears your account.
- Ignoring bond notice deadlines: A perfect mechanics lien doesn't help if you missed a 30-day bond notice deadline on a bonded project.
Your Next Action
Calculate your critical dates today. Mark the preliminary notice deadline, mechanics lien deadline (90 days from last work), and any payment bond deadline. If you're unsure of deadlines for your state and project, check the official agency website or confirm with an attorney familiar with construction law in that jurisdiction.
At 60 days unpaid, don't delay—file your mechanics lien while you have time. Court recovery is slower, more expensive, and often yields less than the full amount. A recorded lien is your strongest negotiation tool. LienWarden computes these deadlines for all 50 states and drafts the notices and lien documents to meet local requirements. Your first active project is free, so you can start calculating without cost.
Related guides
- What Is a Preliminary Notice? Skip It and Lien Rights Can Vanish
- What Is a Mechanics Lien, and What Do You Lose by Filing Late?
- Payment Bond: What Happens If You Miss the Deadline?
Questions people ask
What's my first move if the GC hasn't paid me after two weeks?
Send a written demand for payment immediately by certified mail. Then check whether your state requires a preliminary notice filed within days of your first work—some states mandate this within 10–15 days, and skipping it voids your mechanics lien rights even if you file it on time. If you haven't filed it and the deadline remains open, file now.
Does filing a mechanics lien guarantee I'll get paid?
No, but it creates powerful leverage. A lien attaches to the property itself, preventing the owner from refinancing or selling until it's resolved. This pressure often breaks deadlocks. However, you still must pursue collection through bond claims, negotiation, or court if the GC doesn't respond.
What's the difference between filing a mechanics lien and a payment bond claim?
A mechanics lien is recorded against the property; a payment bond claim targets the bond issuer's insurance policy. Each has its own deadline—bond notices often expire in 30–90 days depending on the bond type and state, while mechanics liens typically allow 90 days. Both can exist on one project.
If I miss the preliminary notice deadline, do I lose all payment options?
You lose mechanics lien rights in most states, eliminating your strongest tool. You may still recover through payment bond claims, lawsuit, or collection, but those paths are significantly slower and more expensive. The preliminary notice deadline is costly to miss—verify it immediately upon starting work.
Stop chasing invoices. Start collecting.
LienWarden computes every lien deadline in all 50 states from your project dates, then drafts and delivers the demand letters and notices — email included with paid plans, certified mail $19 flat. Your first active project is free.
Start free — no card requiredUse LienWarden free
Your first active project is free. LienWarden computes every notice and lien deadline in all 50 states from your project dates and drafts the documents.
Use LienWarden free →